1999 Annual Operating Report
Boston Groundwater Trust
The Board of Trustees of the Boston Groundwater Trust is pleased to present the following report of the Trust's
operations during the past year and also to outline our program for the year 2000. We are grateful to the City
of Boston for agreeing to fund our ongoing groundwater-monitoring program. And we acknowledge the cooperation
of Wentworth Institute of Technology interns, Chris Simonelli and Matt White, who have been "in the field"
taking readings, and the invaluable assistance of James R. Lambrechts in initiating that project in 1999.
Thanks to these efforts, in place now is the first regular monitoring program since deteriorated groundwater
levels and serious foundation damage were identified in the 1930's. This is a momentous achievement that has
important consequence for the City of Boston.
Additional thanks are due to sponsoring civic organizations that have made their nominees available for Board of
Trustee service following appointments in 1997 by Mayor Menino.
Our hope now is to significantly increase the number of well sites being monitored. Toward that goal, important
financial support from The Raymond Property Company and Boston Properties has made possible contemplation of a
first phase expansion plan, which is currently scheduled for later this year. Trustees are now pursuing capital
improvement funding to further enlarge the well network from the current 100 locations up to 1000 wells in the
next two years.
6/5/00
ACCOMPLISHMENTS IN 1999
BOSTON GROUNDWATER TRUST
A summary of accomplishments of the Boston Groundwater Trust in 1999 are listed below:
- Groundwater Level Data Base Development: Computer software was adapted to
storage and retrieval of groundwater level data. Excel spreadsheets have been set up to
store and retrieve this data.
- Base Plans: CAD Files were obtained from BWSC that provide base maps showing
streets, buildings, and utilities in the study area, and on which the observation well
locations have been superimposed. An interface between database and CAD plan is
being developed. Plans are related to the Massachusetts Plane Coordinate system.
Locations of observations wells entered in CAD plan system based on measurements
made in Task No. 6.
- Solicitation of Groundwater Level Data from Private Parties and Public Agencies:
With H&A knowledge of activities by various developers, building owners, and city
agencies, letters were prepared and sent requesting access to data on groundwater ele-
vations, and on observation well locations for specific projects in the study area. Some
data have been received. More follow-ups are needed.
- Locating Observation Wells and Determining Working Condition: Field work was
done in 1999 to locate each observation well shown to be functional in the 1990
inventory report by Stone & Webster. Subsequently other observation wells were added
as found in public sidewalks (many of which had been installed by those parties contacted in Task No. 3.)
- Measuring Groundwater Elevations in Functional Observation Wells and
Recording Data: Measured groundwater elevations in each well. (Four to six
readings made for the year, at about two per semester). Data was entered in the spread-
sheet database, and summary tables were produced for each monthly meeting of the
Trust.
- Surveying to Determine Observation Well Reference Elevations and Field
Locations: A team of two Wentworth Institute of Technology co-op students performed
level surveying to determine the ground elevation of each well, using references to
established elevation benchmarks that are throughout the Back Bay (determined from
data on elevations of reference benchmarks currently in use by H&A). Plan measurements were also made by the
pair from existing features shown on the base maps to locate each observation well, for inserting on locations
in the CAP mapping files. Wells are predominantly located in areas where buildings are on steel or concrete
piles.
Very few of the wells are in areas of wood pile foundations.
- Purging Water from Observation Wells to Verify Functionality: Each well was tested
for groundwater level recovery rate by withdrawing approximately 2 to 4 gallons of
water, determining achievable water level lowering, and monitoring groundwater level
recovery. Wells in which the water level could not be lowered significantly were deemed
to be functioning adequately. Wells which recovered to near or slightly above their
initial levels within a few hours were also judged to be adequate. Only 9 out of the 152 wells that were purged
were considered to have poor/unacceptable response (and have been marked for needing revitalization, or deletion
from the program).
- Report of Period Activities: The two co-op students prepared brief summary reports
that included tables of data and plans indicating the groundwater elevations of each well.
YEAR 2000 PROGRAMS
BOSTON GROUNDWATER TRUST
Activities planned by the Boston Groundwater Trust for the year 2000 are as follows:
- Measurement of Groundwater Elevations: Continue to measure all operable
observation wells at least three times per semester (approximately 10 readings per year).
Continue to update database with new data from these readings, within one week of the
readings. Develop study area plans to summarize "problem" areas with groundwater
levels below Elev. +6 BCB as each set of new elevations are gathered.
- Prepare for and Monitor the Installation of New Observation Wells: Prepare plans and forms for P.I.C.
authorization for each proposed new observation well location. Solicit cost proposals from 3 different drilling
companies for making the Phase I observation well installations. During the installation of new observation
wells in the Fenway/Symphony and Back Bay areas (where about 125 new wells are needed). Monitor the drilling
contractor's installation of each new well and document details of each installation in the database.
- Building Permits Search at Inspectional Services: Research files/permit jackets at ISD
to determine extent of areas of wood pile foundations at the perimeter of the principal study area. Areas
identified will also be included in further study of groundwater levels.
- Base Plans: Continue work on the plans, ensuring that all wells are properly located.
Obtain updated databases from BWSC (or BRA) as available to correct certain building
locations.
- Collection of Groundwater Level Data from Public and Private Parties: Update
database with new well data being obtained from various developers, building owners
and city agencies that agree to being in the program. Expand the database to allow
including groundwater level data from previous years.
- Locating Additional Existing Observation Wells: Continue to search for other existing
observation wells, which were not identified in the 1990 report by Stone & Webster, or
were recently installed. Determine ground surface elevations by level surveying for new
wells. Use any additional information provided by other parties (from No. 5 above), to
locate additional wells.
- Launch of Web Site: Reformat and maintain mapping and well monitoring data for public accessible display,
on-line.
YEAR 2000 OPERATING BUDGET
BOSTON GROUNDWATER TRUST
I. Wentworth Co-op Researchers: $43,640
First Student @ 3 semester per year @ 17 weeks
per period. One Student @ 40 hrs/wk @ $16/hr
=$640 dollars/wk x 51 wks
=$32,640 dollars/yr for one student
Second Student for summer period of 17 weeks of
field work (1/3) = $11,000 (Supervision of new
observation well installation).
II. Reimbursable Expenses: $ 3,900
-Field Equipment & Related $ 3,500
-Office Supplies, Reproduction, Postage $ 400
III Web Site: $10,000
-Development, Updating, Maintenance
and "Rental" ______
Sub-total $57,540
10% Contingency $ 5,754
TOTAL CALENDAR 2000 OPERATING BUDGET $63,494
CAPITAL NEEDS BUDGET - YEARS 2000, 2001, 2002
BOSTON GROUNDWATER TRUST
In order to establish observation of groundwater levels at the frequency and distribution of locations as
recommended by engineering analysis for the 2000 acre area of the City of Boston deemed vulnerable to possible
foundation deterioration, the Trust envisions a critical need to expand the monitored network. The Trust
estimates that the following three phased incremental budget will result in an increase in the number of wells
observed to a required network of 1,000 locations. Trustees are now seeking commitment of funds to make these
capital improvements possible.
The following cost estimate for installation of one (1) observation well in year 2000 is based on a minimum
quantity of 20 wells per contract and included here for reference in analyzing the projected annual budgets
below:
Items: Budget:
Material $250
P.I.C. Permit $350 *
Street Permit $250
Rig/Crew Labor $800 avg.
Police Detail $160
Utility Clearance $100
Total $1,910
*A request would be made to have this fee lowered by the P.I.C.
YEAR 2000 CAPITAL BUDGET
Phase I - Expansion of Observation Well Network at Existing Critical Locations
$50,000.
Install approximately 25 new monitoring wells at critical locations in Back Bay
and Fenway/Symphony areas @ $2000 each.
YEAR 2001 CAPITAL BUDGET
Phase II - Expansion of Observation Well Network
$1,000,000.
Install approximately 500 new observation wells @ $2000 each. This will achieve an averaged density of one well
per 2 acres, as baseline coverage similar to that of the WPA Program in the 1930's.
YEARS 2002 / 2003 CAPITAL BUDGET
Phase III - Expansion of Observation Well Network in Areas of Lower than Normal Groundwater Levels
$1,200,000.
Install an estimated number of 500 new observation wells, @ $2400 each. Following observations of the then
expanded monitoring well network, specific areas of lower than normal groundwater will be investigated. Those
areas identified as having levels below minimum "safe" elevations will require these additional wells to be
installed to further define the location of lowered groundwater.
Engineering analysis estimates that 15 such Low Groundwater Locations will be identified in the first two years
after Phase II wells have been installed. Using an average of 30 wells as being needed to "localize" the point
of the lowering and better define an approximately three blocks local area of severe impact results in the
projected need of 500 additional observation wells.
An estimate of the average cost of $2,400 per well is used due to the limited number of wells to be installed at
any one time, and the cost to mobilize/demobilize for each series of field installations.
|