6/27/05
Hello everyone. The following summarizes our work 6/04/05 - 6/27/05:
- Installed and incorporated all 59 wells to complete 105 contract.
- Began installation of contract for 114 wells. Have installed 9 wells as of today 6/27/05.
- Completed all May/June 05 readings for all 529 wells in the network. Latest readings and revised map with new well locations are now posted.
- Received 3 bids for next group of 180 wells and prepared bid analysis.
- Received invoice for 59 wells installed by NHB and I am in the process of preparing an invoice analysis.
- Visited a residence in East Boston, on London Street, and discovered that the building has a wood pile foundation.
I will continue to be both in the field and the office coordinating the overall activities.
If you have any questions please feel free to contact me.
Kind Regards,
Christian Simonelli
BGwT Technical Coordinator