Reports: Technical Coordinators’ Updates, 2005

2005 Technical Coordinator Report #13

09/12/05

Hello everyone. The following summarizes our workÊfrom 8/15/05 - 9/12/05:

  • Continued installation of contract for 114 wells. Have installed 101 wells as of 9/12/05.
  • Updated database to include all new o.w.’s that have been installed.
  • Next set of readings will begin tomorrow 9/13/05.
  • Rehired Ashley Keepers for the Fall/Winter semester. Also have kept Stephen Guarente on as a part-time employee.

I will continue to be both in the field and the office coordinating the overall activities.

If you have any questions, please feel free to contact me.

Kind Regards,

Christian Simonelli
BGwT Technical Coordinator