10/24/05
Hello everyone. The following summarizes our work from 10/04/05 - 10/24/05:
- Have installed 27 of the 180 wells so far.
- Wells have been installed in Fort Point Channel area and will be installed in East Boston. These wells mark the first BGwT o.w.s ever installed in these areas.
- Updated database to include all new o.w.s that have been installed.
- Uploaded first set of Fall 05 readings.
- Will begin second set of Fall 05 readings this week.
I will continue to be both in the field and the office coordinating the overall activities.
If you have any questions, please feel free to contact me.
Kind Regards,
Christian Simonelli
BGwT Technical Coordinator