Reports: Technical Coordinators’ Updates, 2004

Technical Coordinator Report #11

Hello everyone. The following summarizes our work in the week ending 25 June 2004.

  • Installed 8 observation wells and incorporated them into the network.
  • Prepared 10 observation well locations for installation.
  • Received Bid sheet for the next group of 125 observation wells from one (1) of the six (6) Drilling companies. Others are forthcoming and are due 30 June 2004 by 4:00pm.

I will continue to be both in the field and the office coordinating the overall activities. If you have any questions please feel free to contact me.

Kind Regards,

Christian Simonelli
BGwT Technical Coordinator/Environmental Engineer