The following summarizes our work from 22 November - 13 December 2004.

  • Completed winter ’04 set of readings and uploaded latest readings, locations, and map.
  • Incorporated remaining 33 o.w.’s into the network.
  • Hired winter ’05 co-op Ashley Keepers. Ashley is set to begin her co-op the second week in January ’05.
  • Continued work on Bid document for the EPA program of wells to be installed in the Spring/Summer 2005.
  • Continued to work on alternate solutions for groundwater recharge.

I will continue to be both in the field and the office coordinating the overall activities.
If you have any questions please feel free to contact me.

Kind Regards,

Christian Simonelli