Technical Coordinator Report #3

Hello everyone. The following summarizes our work in the week ending 7 May 2004.

  • 10 observation well locations have been cored and vacâed. These wells are scheduled to be installed next week 10-14 May 2004. Four of the proposed locations must be moved and dig-safed. Various attempts were made on all four proposed locations and were unsuccessful.
  • At the last minute, Alex Marinkovich decided to take another summer co-op leaving us only with Derek Barnes. Derek is still scheduled to start on 17 May 2004. The search continues for an additional co-op.
  • I will continue to be in the field coordinating the overall activities. If you have any questions please feel free to contact me.

Kind Regards,

Christian Simonelli
BGwT Technical Coordinator/Environmental Engineer