Hello everyone. The following summarizes our work in the week ending 11 June 2004.
- Obtained PIC permits for 22 of the next 60 observation wells to be installed.
- Obtained ISD building permit for the next 60 observation wells to be installed.
- Scheduled the start of installation for the group of 60 wells for Monday 14 June 04.
- Spring (May 04) readings, locations, and map are now up on the web-site.
- Continued to work on preparing the Bid document and PIC for the next 125 wells to be installed.
I will continue to be both in the field and the office coordinating the overall activities. If you have any questions please feel free to contact me.
Kind Regards,
Christian Simonelli
BGwT Technical Coordinator/Environmental Engineer